The South Pars gas field in the Persian
Gulf, 100 kilometers from Iran’s Southern coastline is shared by Iran and
Qatar. The field's first exploratory well was drilled in 1990.
In order to develop the gas field Iran’s
oil ministry set up the Oil Engineering and Development Company. Since
adequate funds were not available for the development of this gas field in the
period immediately following the 1980-1988 Iran-Iraq war, the High Council for
Economy decided to execute the project on a buyback basis.
South Pars gas field is a huge and
unique field containing 8% of world’s gas reserves.
Recent seismographs and studies indicate
that gas deposits in Iran’s portion of South Pars gas field is more than it
was originally estimated. The volume of deposit in this field is some 13
trillion cubic meters that makes up 50% of the country’s total gas deposits.
The volume of liquid natural gas (LNG) in this field is estimated at 17
billion barrels, which will most probably be more than the original estimates.
The first development phase of this
field after a 20% progress was awarded to Petropars, which is an Iranian
company registered abroad.
12 wells on two platforms are already
drilled in this phase and construction works for on-shore refineries is 96%
complete. Furthermore, some units have already been commissioned. In addition,
as a result of installing production and residential accommodation platforms
for some 100 staff, meshing of wells and lying of seabed pipe lines, the first
phase of South Pars gas field will be operational in the near future.
|
The difference between phases 1 to
8 with phases 9 and 10 is that the former phut
the latter phases areases are buyback b
being implemented on a finance basis. |
The main partners for the projects are
Iran’s Industrial Promotion and Renovation Co. and South Korean Dailem Co.
with the utility sector left to the Iranian Mabna Co. entirely, which has
employed a 60% majority of Iranian contractors and consultant engineers for
the execution of the project.
Contracts for phase 2 and 3 were signed
in 1997 on a buyback basis. The preliminary operation of the phases started on
March 2001. The contractor for this sector is a consortium of French Total,
Malaysian Petronas and Russian Gasprom, with 40, 30 and 30% shares
respectively. The prime contractor of the refinery is South Korean Hyundai
Company, which has employed 36 Iranian sub-contractors for construction.
Contractors of phases 4 & 5 are Iranian
Petropars and Italian Ajip with 60% and 30% shares respectively.
Following awarding of contracts for the
mentioned phases, 20% of shares was sold to Nico Co. and there are three
companies working on this project now. Contract for these phases were signed
in mid-2000 and its first unit will become operational by 2004.
Work on this project is going according
to plan and upon commissioning, 50 million cubic meters of gas; 80,000 barrels
of LNG and 400 tons of sulphur will be produced daily in this sector.
According to initial estimates these two
phases will produce one million tons of LGP and one million tons of ethane
annually. Ethane is used by petrochemical plants and has high added value.
Phase 6, 7 and 8 of South Pars gas field
is also designed for production of 80 million tons of sour gas per day and it
is intended that after sweetening and separation of liquid gas and adjustment
of the dew point, the dried gas be transferred by a 512 km pipeline and
through 4 pumping stations to Aghajari in the south of the country for
injection into oil well in this region. In addition, some 500,000 tons of LPG
in these phases will be separated and along with 120 tons of LNG will be
exported to cover construction costs.
For implementation of these phases,
three off-shore production platforms will be constructed and they will be
connected to the refinery by three 32 km and 105 km pipelines. Contracts for
the construction of pipelines, jackets and topsides for these phases have been
concluded and Petropars chose Norwegian Statoil as its partner for
implementation of this project.
Petropars is the prime contractor of the
three phases and 40% of off-shore projects were awarded to the company
recently, but Statoil will undertake off-shore works which, given the
Norwegian’s experience in the field, is an appropriate decision. Working
off-shore is a new endeavor for Petropars and it will gain valuable
experiences. The construction of on-shore refinery has been put on tender and
winner will be announced soon.
Phase 9 & 10 of south pars gas field are
intended to produce 50 million barrels of LNG, one million tones of LPG and
one million tons of ethane per day.
The refinery contract was signed in 2002
and its contractor is a consortium headed by LG Engineering and Oil Industry
Construction Company from South Korea together with Sea Installation Company
of Iran. In this project, 60% of projects have been awarded to two Iranian
contractors and the South Korean contractor will carry out the remaining 40%.
The difference between phases 1 to 8 with phases 9 and 10 is that the former
phases are buyback but the latter phases are being implemented on a finance
basis. The contractor has already submitted the letter of guarantee and in
order to expedite the project, the contractor has received advance payment.
Phase 9 & 10 like other phases have two platforms and 24 active wells and
output will be transferred to the shore by two pipelines.
The sweetening refinery for these phases
is located on the mainland and the project is similar to phases 4 and 5.
The location of phase 11 and 12 is
outside Assaluyeh region, 70 km West of Assaluyeh in the direction of Bushehr
in a region called "Tonbak". These two phases together with phase 13 are
designed for LNG production.
Tender documents for phases 11 and 12
have been distributed and technical studies have been made. The winner of the
tender for phase 11 will be announced in the near future.
Concerning phase 12, it has been decided
to drill another descriptive well, gather further data and pass it over to
bidders to enable them to submit more precise proposals. Facilities for phase
13 will also be installed in Tonbak region.
Phase 14 is designed for production of
GTL and the objective is to convert the natural gas into semi-distilled
products, which is a new technology.
14 phases have been determined so far
and contracts for 10 phases have been concluded and formalities for awarding
contracts for the remaining four phases are underway.
A new oil field, parallel to the gas
field at 1000 meters below the sea bed, has been discovered but due to a lack
of adequate information on this new oil field, proposals made by contractors
for development of the field were shelved for a time, until a descriptive well
was drilled and enough data was gathered. After drilling the exploratory
well’s production was estimated at 5,000 bpd. Tender documents have been
issued for further first phase development of this oil field to increase daily
output to 35,000 barrels and it is hoped that additional developmental phases
will bring its production volume up to 100,000 barrels per day.